[Click to enlarge ]
Mexican tiles upstairs.

Mary Ann's Tropical Building Page

Report #19: December 29th, 1998

Part 4 of 4

Warning: This report is so long and has so many photographs that we decided to break it into several parts. To return to the start of this report, click RESTART when you get to the end of this segment.



More Floor Tiles


[Click to enlarge ]
Entry is tiled.

Upstairs the Mexican tiles are laid diagonally, with a border of the same tiles around them. The picture at the top of this page shows the final upstairs wall color well.

The next picture shows the entry to the technology center. There will be sliding louvered doors between the tiled entrance hall and the carpeted main activity room. (By the way, the carpeting and drop ceiling improved the acoustics dramatically over hard concrete and tile.)


[Click to enlarge ]
Uses for broken tile.

We had lots of broken Mexican tiles, so we decided to incorporate them into a design.


[Click to enlarge ]
Please put me on the Net.

This work was done by Emo (top photo) and his assistant, pictured here laying tile on the wall around the palm tree.


[Click to enlarge ]
Entry porch.

Entry porch uses broken tiles also, as a border between the diagonal tiles and the horizontal tiles.

The step up to the porch is an irregular wave shape and covered with a mosaic of broken tiles as well.



Continuing the Main House Foundations


[Click to enlarge ]
Waterfront cistern floor.

This cistern goes under the master bedroom porch. Since the master bedroom is raised up about six feet over the surrounding ground level, it was relatively simple to insert a cistern here.


[Click to enlarge ]
A sunken cistern.

This cistern goes outside the kitchen. It is at a lower elevation than the master bedroom cistern and catches water from the lower roofs. The space to the right of it is reserved for a swimming pool (we are still looking for design and construction input on the pool).


[Click to enlarge ]
Pouring the concrete.

West Indies Concrete poured this concrete, although we have used all three concrete companies in the project so far. That is Binger handling the hose and our contractor Geoff Richardson in the background.


[Click to enlarge ]
Master bedroom foundation

You can now start to see how the main house will be laid out across the waterfront.

The End. Click here to RESTART



Site Map: Links, Plans and Other Info

Latest News from our Construction Site

Past and Future Progress Reports

Plans of the Main House

Plans of the Software Center

Plans of the Guest Villa

Tropical Construction Bookstore

Links to Related Sites

Building Material Sources


Beach Shack Contact:

Mary Ann Green
Box 931, Shoal Bay, Anguilla, West Indies
Fax: 264-497-3295
[Home] [Mail] URL: www.beachshack.ai
Email: [email protected]